Utilities crack down on phantom data center claims
The gist
Utilities and regulators are slamming the brakes on AI data center power requests, exposing just how much of the supposed demand was pure hype.
What to know
- More than 1,000 GW of new grid requests—mostly for data centers—have piled up, but strict screening in Ohio and elsewhere has slashed real deals to a fraction.
- Developers are inflating the queue by submitting duplicate applications across multiple utilities, warping planning and stalling real projects.
- With $29 billion in utility rate hikes proposed for 2025 and over 100 local moratoriums, consumers risk paying for phantom projects that may never be built.
Reality Check for Power Claims
Stricter financial screening has slashed speculative data center requests, revealing that much of the projected AI-driven demand never advances beyond the paperwork.
By late 2026, the interconnection queue had become the clearest place where AI power demand claims were being stress-tested against reality. Data Center Knowledge reported that in Ohio, American Electric Power received more than 30 GW of preliminary data center load requests, but after stricter financial requirements under its Data Center Tariff process, only about 13 GW advanced to formal load studies and 5.6 GW reached signed service agreements, a sharp culling that showed how much queued demand had been speculative rather than truly deliverable.
That same August-to-November turn toward queue skepticism was visible beyond the U.S., as regulators shifted from accepting headline demand to testing project readiness. The IQ-EQ and Sustainable Real Estate Forum study noted that UK data center demand in the grid connection queue stood at roughly 73 GW as of mid-2025 and that reforms would now test readiness; in the Netherlands, unused contracted capacity can be reclaimed after about two years; and the EU’s proposed Cloud and AI Development Act aims to triple data center capacity within five to seven years while, for the first time, linking the designation of acceleration zones to available grid capacity, storage, and clean power.
Grid Chaos from Duplicate Filings
Developers inflating demand with overlapping applications have jammed the system, forcing utilities to plan for phantom loads that will never materialize.
The distortion starts at the application stage: Crypto Briefing described developers filing overlapping requests with multiple utilities at once to shop for the best connection terms, while each utility records the full load as if it were unique demand. That is how utilities ended up receiving requests for 1,066 gigawatts of new electricity capacity even though Wood Mackenzie estimated only about 28% was likely to result in anything actually built; as one case study put it, “A queue that is free to join fills with requests that were never going to be built, and the announced number tells you more about the entry price than about demand.”
The mismatch is already visible in operating data and utility behavior. As of ERCOT’s March 2026 update, 9,042 megawatts of large load had received Approval to Energize, yet the most ERCOT had ever seen them draw at once was 3,883 megawatts, against 445 gigawatts requested; in Ohio, AEP halted new data-center requests after more than 30 gigawatts of applications, and after contracts required developers to pay for 85% of reserved capacity, the pipeline fell sharply. That matters because phantom applications consume interconnection slots and delay the queue—so a project expected in 2026 might not connect until 2029—while inflated planning signals can justify substations and lines that end up underused.
Utilities Raise the Bar for Access
Tougher entry requirements and local moratoriums now force data center projects to prove their legitimacy before securing scarce grid slots.
The response is no longer theoretical: utilities and governments are actively narrowing the front door. On Closing Bell, Texas’s queue was described as having “stretched to 474 gigawatts, 90% of which are data centers,” and “that’s what led Governor Abbott to institute the pause on new applications,” while the same interview said utilities are already imposing stricter criteria to secure a place in line, a sign that queue access now depends more on demonstrating a project is real rather than merely early. That broader pullback is also showing up at the local level: the content states that “100+ US municipalities or localities… have enacted as some form of a data center moratorium or ban in 2026,” and cites specific actions including the “New York legislature passed a one year 20 megawatt permitting” restriction.
That tightening is spreading beyond outright pauses into financial and contractual screening. San Francisco Business Times reported that utilities are demanding study deposits, take-or-pay minimums, longer service commitments, collateral or credit support, upgrade contributions, and even phased energization, while Reuters analysis cited AI-linked bond spreads at around 115 basis points versus 78 for the broader investment-grade market, reinforcing a climate in which speculative applicants face higher proof burdens before utilities or counterparties will treat requested load as commercially serious.
Consumers Foot the Bill for Overbuild
Massive infrastructure spending—based on inflated demand—means ratepayers are already facing billions in higher costs even as many projects may never use the grid they’re paying for.
The consumer risk begins with how regulated utilities get paid: once transmission lines, substations, transformers, or new plants are approved, those costs can enter rate base and be recovered through customer bills, plus an allowed return. Odd Lots cited an analyst who said data centers use “around 45 gigawatts of power” today and may need only about 50 more by 2035, yet utilities already have roughly comparable supply in progress; even so, “Just yesterday Nextera moved another 2 gigawatts from the potential into the committed,” showing how spending commitments can outrun credible load.
That matters because the buildout is expensive, slow, and broadly socialized: AI load growth has jumped from roughly “0.5% annually” over the last 30 years to “2.53% per year,” while “it takes six to seven years to build a new power plant” and “seven to nine years to build a new transmission line.” As one analysis put it, adding grid capacity is like widening a highway: “It’ll take you 10 years, and it’s very expensive, and everybody pays for it” — even though “AI data centre globally grew by 50% in their energy consumption in just over a year,” a pace that can reverse before the assets are fully used.
The bill impact is no longer theoretical: The Long Memo reported that in the first half of 2025, utilities sought more than $29 billion in rate increases, affecting 40 million customers, with data centers repeatedly cited as the reason. RMI noted utilities are planning large, long-lived assets for named customers — including Entergy’s more than 5,200 MW for Meta in Louisiana and nearly 10,000 MW approved for Georgia Power — but warned that even with contractual protections, those assets may be underused if the load arrives late, smaller than expected, or never materializes.